- Do you know how to manage the project initiation?
Start
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1
Which of the following outputs should not be completed during the project initiation phase?
A
A project budget
B
A high level project plan
C
A data management plan
D
A list of required resources
Question 1 Explanation:
Yes, the correct answer is a data management plan. Outputs during the project initation phase include an initial project plan, budget and resource plan. The data management plan can be developed at a later time.
Question 2
Your project plan and budget should be final, all-inclusive versions during the project initiation phase?
A
True
B
False
Question 2 Explanation:
Your project plan and budget will not be a final, all-inclusive version during the project initiation phase, but you will need a high level plan and budget that may be revised as your period of active research nears.
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 2 questions to complete.